Scenarios
When you create an execution task and enable the batch pause function, you need to manually start the next batch of task operations after the task is paused.
This applies to scenarios where you need to manually resume the task after each batch of operations is completed and you have confirmed that the instances that complete the operation meet expectations.
Prerequisites
After one batch of the task is completed, the task enters the Waiting status.
Procedure
- In the top menu bar, select the project and region of target resource.
- Click the name of the scaling group and select the "Rolling Upgrade" tab.
- Click the task in Waiting status, and then click the "Continue" button.
- Click the "Confirm" button to complete the operation.