Creating a failure drill task
Copy page
Download PDF
Creating a failure drill task
Scenarios​
In a scenario where a new Direct Connect (DC) link accesses the data center, you can perform a failure drill to verify the reliability of the DC Connection and BGP Peer redundancy failover.​
Prerequisites​
  • You have completed networking between your on-premises data center and the Virtual Private Cloud (VPC). For procedure, see Quick start for Direct Connect.​
  • You have completed redundancy configuration for related drill objects.​
  • BGP Peer: Configure multiple BGP Peers for the DC Virtual Interface based on Adding a BGP Peer.​
  • You have configured relevant event monitoring for the DC Connection in Cloud Monitor. Learn more​
Procedure​
  1. In the left-side navigation pane, select Failure Drill.​
  1. Click Create task and configure the parameters based on the table below.​
  • ​
    Parameter​
    Description​
    Example​
    Basic information​
    ​
    ​
    Regions​
    Select the region to which the failure drill object belongs.​
    Private networks in different regions are isolated. We recommend selecting a region closest to your business for lower network delays and faster access.​
    China (Beijing)​
    Name​
    Set the failure drill name.​
    Fault-test-dc-01​
    Task configuration​
    ​
    ​
    Drill object​
    You can only add resources whose status is Available as drill objects. When the failure drill task runs, the system sets the drill object's status to Faulty or Unavailable.​
    • DC Connection: DC Connections associated with cross-account resources do not support failure drills.​
    • BGP Peer: Only BGP peers whose session status is Up support failure drills.​
    DC Connection | dc-01​
    Drill now​
    • Enable drill now: The failure drill task starts immediately after creation.​
    tip​
    Ensure you have completed redundancy configuration. Otherwise, the failure drill may cause service disruption.​
    Disable​
    Drill duration​
    Set the failure drill duration. Set at least 1 minute, and at most 72 hours (4320 minutes).​
    180 minutes​
    ​
  1. Click Create to complete the action.​
What to do next​
  • (Optional) Start a failure drill: For a failure drill task without Drill now enabled, you need to start the failure drill manually.​
  • View event monitoring: After the failure drill ends, you can review DC event alarms to confirm that the redundancy failover was triggered and executed successfully in the failure scenario. If you receive a DC-related alarm from Cloud Monitor, it means the drill object cannot switch lines/routes as expected. Check the relevant configuration.​
Related documents​
CreateFailoverJob: Create a failure drill task.​